← Back to the proposal

Sources & Verification

Are these numbers real?

Every claim in the proposal, checked against primary sources — independently, in July 2026 — with the link and an honest verdict on each. The core numbers hold up. Four needed a correction; those have now been fixed in the paper and the PDF, and are documented here in full.

The short answer: yes — and the four corrections are now applied.

The load-bearing quantities are real and sourced: La Osa's 3,385 acres, 3 GW (as-proposed) and $33B; the aquifer's 8-million acre-foot shortfall; the grid's 280 MW district peak; Griffin's 2,685 acres / 550 / 500 MW; the $2.68 water-bill figure; and the Gift Clause case law. Each links to a primary filing, a government source, or established reporting below.

Verification turned up four things to fix — a wrong utility, a mislabeled number, a case described backwards, and a cooling term. All four are now corrected in both the on-page proposal and the downloadable PDF; the record of what changed is kept in the box below for transparency.

⚠ What changed after the paper was written

The proposal is dated May 28, 2026 and flagged the May 27 La Osa outcome as unconfirmed. It has since resolved: at the May 27 hearing the Board continued the vote 3–1 to August 26, 2026, and the developer (Vermaland) cut La Osa ~80% — from 59 data-center buildings to about 11, and from ~3 GW toward ~1 GW. So the paper's La Osa scale figures were accurate as proposed; the live project is smaller. The framework applies at any size.

✎ Corrections found in verification — now fixed in the paper

All four below have been corrected in the live proposal and the downloadable PDF. Kept here as the record of what changed.

  1. Project Midway — utility and number. The paper lists Midway as “≈225 MW baseline grid power · SRP.” In the record it is in Electrical District No. 3 (ED3) territory, not SRP, and the applicant had no power contract; the “225” is 225 permanent jobs, not megawatts — there is no published MW figure. Pinal Post
  2. Marigold — which body votes. The ~600 / 400 / 675 MW figures are right, but the “Board vote targeted Summer 2026” is SRP’s own board approval, not a Pinal County Board of Supervisors vote. Pinal Post
  3. Rodgers v. Huckelberry — described backwards. The paper cites it as having “voided a county building a facility for one tenant and leasing it back below market.” The trial court did void it, but the Court of Appeals reversed and ruled for Pima County — the below-market World View lease was upheld, and the court expressly did not reach the Gift Clause. It supports economic-development leases; it doesn’t condemn them. FindLaw — Rodgers v. Huckelberry
  4. Microsoft comparison — cooling term. The “hundreds of thousands of gallons per day” water draw is real (WI records show ~234k–702k gal/day), but Microsoft’s Mount Pleasant/Racine campus is marketed as closed-loop “zero-water-evaporation” liquid cooling, not “air-cooled.” The water figure holds; the label should say closed-loop. WPR
What's cited, and what's ours. The framework itself — the two pillars, the three-layer exit, the load-not-labels rule, and every policy recommendation — is the author's original design and stands on its own reasoning. Everything factual underneath it — the water science, the cooling engineering, the case law, the local project numbers — is sourced here. Conclusions are ours; facts get credit.
✓ Verified confirmed against a primary / authoritative source ⚠ Changed real when written, changed since ✎ Corrected was off — now fixed (see the box above) ◐ Caveat real mechanism, modest magnitude

The projects

La Osa is 3,385 acres, carries 33 PAD stipulations; P&Z recommended the rezone 7–2 on April 16, 2026; CPA approved Nov 19, 2025.
✓ Verified
Pinal Post and AZBEX report the 3,385-acre figure, the 33-stipulation PAD overlay, the April 16 2026 P&Z recommendation, and the Nov 19 2025 Comprehensive Plan approval.
La Osa: up to 3 GW of compute and a reported $33 billion — as proposed.
⚠ Changed
Data Center Dynamics and AZ Big Media confirm $33B / 3 GW at proposal; both the GW and the building count were cut ~80% in late May 2026 (see the orange box). 3 GW was the original ceiling.
La Osa grid + water interface: WAPA 115kV + APS 230kV, Electrical District No. 4, Global Water.
✓ Verified
Per the application: WAPA owns the 115kV lines crossing the property, APS the 230kV line on the southern parcels; ED4 is the delivering district; Global Water is the named service provider (early phases on wells until demand justifies a plant).
La Osa: up to 2,000 MW of on-site natural gas.
⚠ Changed
The 2,000 MW figure appears as the assumption in the project’s water-memo addendum; the developer’s release says “up to 3 GW,” and at the April 2026 hearing the applicant’s attorney called the number “not set.” Real cited figure, not a fixed capacity — and now subject to the 80% downsizing.
Griffin Energy (PZ-PA-014-25): 2,685 acres · 550 MW solar / 550 MW battery / 500 MW gas · CPA approved Nov 19, 2025 · feeds the W Holdings campus.
✓ Verified
AZBEX and the Casa Grande Dispatch confirm Griffin’s (Copia Power) 2,685-acre re-designation, the 550/550/500 MW figures, the Nov 19 2025 Board approval, and that it is intended to serve the W Holdings data-center campus.
W Holdings “Energy Generation & Technology Campus” (PZ-PA-015-25): ~495 of 2,495 acres · replaces ≈10,600 planned homes · ED3 territory.
✓ Verified
AZBEX confirms the 2,495-acre campus, the “+/-10,600 planned single- and multi-family units” it replaces, and the SR-347 / W Louis Johnson Dr location (inside ED3’s service territory). Sources round the redesignated parcel to “~500 acres”; the exact 495 figure isn’t separately published.
Project Midway (PZ-PA-013-25): 215 acres · ~225 MW · SRP.
✎ Correction
Acreage and the Nov 19 2025 5–0 CPA approval are correct. But the utility is ED3, not SRP, and “225” is 225 jobs, not megawatts — no MW baseline was published, and the applicant had no power contract. See the corrections box.
SRP Marigold Energy Center: 600 MW solar / 400 MW BESS / up to 675 MW gas; Board vote targeted Summer 2026.
✎ Correction
The MW figures are confirmed (≈1,275 MW combined, near Stanfield). But the Summer-2026 vote is SRP’s own board, not the Pinal County Board of Supervisors — the paper attributes it to the wrong body.
Project Bella: 352 acres · 400–440 MW BESS / 480–520 MW gas · comprehensive plan approved & rezoned.
✓ Verified
The Board voted 5–0 on Aug 6, 2025 to rezone 351.8 acres for Project Bella (Seguro Energy Partners) — 480–520 MW gas (10 GE LM6000 turbines) plus 400–440 MW BESS, ~1.5 mi south of Casa Grande.
Frontier East: 160 acres · 50 MW solar / 300 MW BESS · comprehensive plan approved, near the City of Maricopa.
✓ Verified
Frontier East (Sawtooth DevCo, case PZ-PA-011-24): ±50 MW solar / up to ±300 MW BESS on ±159.68 acres near Maricopa, redesignated to Green Energy Production and reaching land-use approval.

Water — the closed basin

ADWR projected unmet groundwater demand of more than 8 million acre-feet, and stopped approving new groundwater-based Assured Water Supply applications. Pinal AMA, 1980 Groundwater Code.
✓ Verified
Straight from ADWR: on June 28, 2021 its Pinal AMA model showed unmet demand exceeding 8 million acre-feet over 2016–2115, and the Department stopped approving new groundwater-based AWS applications in the Pinal model domain. The Pinal AMA is an Active Management Area under the 1980 Groundwater Management Act.
A same-design Microsoft air-cooled campus draws into the hundreds of thousands of gallons per day.
✎ Correction
The water figure is real — Wisconsin records show ~234,000 gal/day (Phase 1) up to ~702,000 gal/day (full campus) at Microsoft’s Mount Pleasant/Racine site, Microsoft citing ~350,000 gal/day on hot days. But the campus is marketed as closed-loop “zero-water-evaporation” liquid cooling, not “air-cooled.” Keep the number; fix the cooling term.

The grid

ED3 peaked near 280 MW in August 2025 — so a 3 GW campus is more than 10× that district's peak.
✓ Verified
InMaricopa reports ED3’s 280 MW system peak as of Aug 7, 2025, across ~36,000 meters. 3 GW = 3,000 MW ≈ 10.7× that peak — the arithmetic holds.
ED4 generates no power and must buy wholesale and resell; and there are 2-to-7-year waits for transformers and turbines.
✓ Verified
Electrical District No. 4 (Eloy) doesn’t generate — it buys wholesale (Parker-Davis/WAPA plus supplemental) and resells to ~2,850 users. Gas-turbine lead times run ~1–7 years (OEMs quoting 5–7; GE Vernova backlog into 2029) and large transformers ~2.5–3+ years — consistent with “2-to-7-year.”

The utility bill

Global Water's rate settlement: ~$2.68/month for the median user, new rates requested effective November 1, 2026.
✓ Verified
Global Water Resources’ own April 29, 2026 filing with the Arizona Corporation Commission: a ~$2.68 estimated monthly increase for the median GW-Santa Cruz user (5,500 gal/mo), new rates requested effective Nov 1, 2026.

The science & engineering

Chronic groundwater overdraft causes land subsidence and earth fissures — documented specifically in south-central Arizona / the Pinal AMA.
✓ Verified
The USGS documents that after ~109 million acre-feet of groundwater was withdrawn (1915–1975) across Pinal and Maricopa Counties, “the land surface has subsided … and earth fissures have developed.” It’s a measured Arizona phenomenon, not a projection.
Evaporative (“wet”) cooling consumes water by evaporating it; closed-loop / air-cooled designs consume little-to-no water on-site.
✓ Verified
The LBNL / U.S. DOE 2024 Data Center Energy Usage Report: “the best facilities today use air-cooled or closed-loop liquid cooling systems that need almost no water at all,” while evaporative towers lose water to evaporation. DOE FEMP confirms the mechanism directly. (Honest caveat both raise: closed-loop can use ~10% more electricity, shifting some water use off-site to power plants.)
The data-center industry is actively shifting away from evaporative cooling toward closed-loop / air cooling.
✓ Verified
Microsoft states all new datacenter designs from Aug 2024 use closed-loop cooling that “consume zero water for cooling,” avoiding >125M liters/yr per datacenter; the independent LBNL report corroborates the broader shift. (The specific liter figure is Microsoft’s own modeled estimate; the trend is independently supported.)
Reclaimed / treated-effluent water can serve data-center cooling, reducing potable and groundwater draw.
✓ Verified
EPA’s Quincy, Washington case study documents RO-treated industrial wastewater “returned to the data center for use as cooling water,” offsetting ~138 million gallons/year of potable groundwater demand.
Water offsets — fallowing farmland, retiring grandfathered groundwater rights, and managed aquifer recharge — are recognized mechanisms to put water back / free it up.
✓ Verified
Under Arizona’s Groundwater Management Code, permanently retiring a grandfathered irrigation right generates extinguishment credits; fallowing irrigated acreage frees water for other use; and managed aquifer recharge is an established replenishment tool. Retiring the right is codified at A.R.S. § 45-463.
Solar arrays double as a stormwater-catchment surface — runoff shed off the panels channels to on-site infiltration and reuse.
✓ Verified
DOE/NREL’s PV-SMaRT work and a Penn State field study (Journal of Hydrology) confirm rain sheds off panels and concentrates at the driplines, and that runoff is directed to infiltration basins/trenches — dripline soil moisture ran ~19% higher than adjacent land. As the paper itself says, the harvested volume is modest (stewardship, not the water solution).
Panel shade cuts soil evaporation and retains moisture (an agrivoltaics finding).
✓ Verified
A peer-reviewed agrivoltaics field study (Barron-Gafford et al., PLOS ONE) found soil under PV panels stayed significantly moister through the season because shade cuts evaporative loss — water-use efficiency up to ~328% higher in shaded rainfed plots.
Solar arrays cut the heat-island effect.
◐ Caveat
The shade mechanism is real — EPA notes shaded surfaces run 20–45°F cooler and shading is core to heat-island mitigation. But for solar PV specifically, the measured air-temperature effect is small (~0.2–0.3 K in one peer-reviewed urban simulation) and context-dependent — panels can even warm surroundings in some conditions. Real, but a modest co-benefit, not a strong cooling claim. Worth softening in the paper.

The legal ground

The Gift Clause (Ariz. Const. art. 9 §7) and its two-part test — Wistuber (1984), Turken (2010), and Schires v. Carlat (2021), which held jobs / growth / future tax revenue don't count as consideration.
✓ Verified
Art. 9 §7 is the Gift Clause (azleg.gov). Wistuber v. Paradise Valley USD, 141 Ariz. 346 (1984) set the two-part test; Turken v. Gordon, 223 Ariz. 342 (2010) (CityNorth) refined the consideration prong to fair market value of what was promised; Schires v. Carlat, 250 Ariz. 371 (2021) held anticipated jobs, economic development, and future tax revenue are not consideration.
Gilmore v. Gallego (2024) as the current Gift Clause precedent; A.R.S. § 11-1101 (development agreements) and § 33-261 (perpetuities).
✓ Verified
Gilmore v. Gallego (2024) is on the Arizona Supreme Court’s own site. A.R.S. § 11-1101 is titled “Development agreements” and authorizes county development agreements; A.R.S. § 33-261 is the “Rule against perpetuities.”
Rodgers v. Huckelberry voided a county building a facility for one tenant and leasing it back below market.
✎ Correction
Real case (Pima County / World View, 2 CA-CV 2017-0091). But the holding is the opposite: the Court of Appeals reversed and ruled for the county — the below-market lease was upheld and the Gift Clause was not reached. As cited, it argues against the paper’s point rather than for it. See the corrections box.

Verified July 2026 against primary filings (ADWR, the Arizona Corporation Commission, the Arizona Supreme Court & Court of Appeals, the Arizona Legislature, Pinal County), the developer’s own announcements, and established regional reporting (Pinal Post, AZBEX, InMaricopa, Casa Grande Dispatch / PinalCentral, Data Center Dynamics, KJZZ, WPR, Utility Dive, RMI). Every link goes to the source, not a summary. The local project figures ultimately live in the Pinal County Board of Supervisors agendas and case packets — the primary public record.

← Back to the proposal